Mr. Kumar is getting his house renovated. 1/5 th of the work has been completed in 2 months. How much time will it take for the entire work to be completed?

Respuesta :

liam2747
liam2747 liam2747
  • 02-05-2021

Answer:

10 months

Step-by-step explanation:

If it takes 2 months to do 1/5th, it will take 4 months to do 2/5, 6 months to do 3/5, 8 months to do 4/5, and 10 months to do 5/5 or in other words the whole thing.

Answer Link

Otras preguntas

Someone plz help me with this problem!!!
what is 5|4x-4|-9=31​
aveWhich of the following is a tax? I. A 1 percent special sales tax for funding local road construction. II. A fee paid to the state for a license to practice
what subject will help you the most after high school
A 200-kg flat-bottomed boat floats in fresh water, which has a density of 1000 kg/m3. If the base of the boat is 1.42 m wide and 4.53 m long, to what depth is t
The temperature in Minneapolis changed from -7 to 7. How much did the temperature increase
A wooden crate of mass m = 70 kg slides horizontally off the back of a flatbed truck traveling at 80 km/hr. Determine the kinetic coefficient of friction betwee
⦁ Explain the difference between ""4 times the sum of x and y"" and ""the sum of 4 times x and y.""
Write a C++ program that reads characters (Upper case, Lower case, and Digits ) including white spaces from the keyboard until user enters ‘#’. Then, your progr
Which equation represents the value of r